This week shows the completion of paving for our property except for the construction entrance. In addition curbing has started in several areas around the main building. The irrigation team is continuing to put in lines around the building.
Several additional internal door frames at the main entrance, children’s church and sanctuary. Electrical wiring continues to be pulled thru out the main building. The main power panel has been delayed due to a failure in the circuit breaker test at the factory. It has affected delivery by over 2 weeks.
The fire alarm system has started installation in the modulars. Also the ceiling tiles were delivered and have started installation.