We are mudding the drywall in various places within the office

and children’s area. Received inspection by our power company

and the City of Clermont on the electrical interface to the modular

complex. All is a go for power. We have requested a power meter

from SECO to allow us to activate the electrical system for the

modulars. The stone company has completed installation of the

stonework on the front of our sanctuary and the columns in the back.

The plumbing contractor is connecting the roof drains to the

underground sewer system. Also starting to work on connecting

the bathroom sewer system from the modular trailers to the property

main sewer system. We poured concrete on both the front entrance

of the main building and the decking for the platform. Steps and ramps

are now completed for the modular complex. Repaired the sprinkler

system in Pond 2 in preparation for sodding Pond #2 behind the modular

complex.

Here is the link for the video of the week.

https://vimeo.com/452742550/0688928950

 

Richard

We are mudding the drywall in various places within the office

and children’s area. Received inspection by our power company

and the City of Clermont on the electrical interface to the modular

complex. All is a go for power. We have requested a power meter

from SECO to allow us to activate the electrical system for the

modulars. The stone company has completed installation of the

stonework on the front of our sanctuary and the columns in the back.

The plumbing contractor is connecting the roof drains to the

underground sewer system. Also starting to work on connecting

the bathroom sewer system from the modular trailers to the property

main sewer system. We poured concrete on both the front entrance

of the main building and the decking for the platform. Steps and ramps

are now completed for the modular complex. Repaired the sprinkler

system in Pond 2 in preparation for sodding Pond #2 behind the modular

complex.