Hancock Project-Week ending 7/25/2020

This week the building project continued to complete the rough in for electrical, plumbing, A/C and remaining amount of framing. Worked with our Audio-Visual contractor to complete the placement of boxes on the sanctuary platform in preparation for pouring the stage. All insulation has been placed on the sanctuary walls and exterior of the Children’s area.  Framed in the AVL booth for the sanctuary. Designed the AVL booth for the Children’s Church. Passed the City inspection of the framing. This will allow us to start putting in the sheet rock on some of the building walls on the exterior. Roof drains are being installed at the front area of the building. Glass contractor continues to install the mullions that will hold our glass.

Outside the contractor formed up the sidewalks on the Northeast side of the building and around to the East side toward the Modulars. Sections of the sidewalk was poured. Work continues on the modulars. Complete sealing the connections between the buildings on both the roof and the flooring. In addition, the electrical connections were finished between each individual trailer. Clean up on the inside including ceiling repairs are underway.

Irrigation contractor installed the remaining water lines and heads for the third pond on our property. Tested the system.

- Richard

Hancock Project-Week ending 7/25/2020

This week the building project continued to complete the rough in for electrical, plumbing, A/C and remaining amount of framing. Worked with our Audio-Visual contractor to complete the placement of boxes on the sanctuary platform in preparation for pouring the stage. All insulation has been placed on the sanctuary walls and exterior of the Children’s area.  Framed in the AVL booth for the sanctuary. Designed the AVL booth for the Children’s Church. Passed the City inspection of the framing. This will allow us to start putting in the sheet rock on some of the building walls on the exterior. Roof drains are being installed at the front area of the building. Glass contractor continues to install the mullions that will hold our glass.

Outside the contractor formed up the sidewalks on the Northeast side of the building and around to the East side toward the Modulars. Sections of the sidewalk was poured. Work continues on the modulars. Complete sealing the connections between the buildings on both the roof and the flooring. In addition, the electrical connections were finished between each individual trailer. Clean up on the inside including ceiling repairs are underway.

Irrigation contractor installed the remaining water lines and heads for the third pond on our property. Tested the system.

- Richard