9/28/2020 Project Update
by: Ron Bloom
09/28/2020
0
This week shows the completion of paving for our property except for the construction entrance. In addition curbing has started in several areas around the main building. The irrigation team is continuing to put in lines around the building.
Several additional internal door frames at the main entrance, children’s church and sanctuary. Electrical wiring continues to be pulled thru out the main building. The main power panel has been delayed due to a failure i...
read more
9/11/2020 Project Update
by: Ron Bloom
09/14/2020
0
This week finds continued work on the property as our
site contractor gets the parking and roadway areas ready
for paving. We have now obtained power on the modular
complex. Working on removing children’s water fountains,
fixing roof leaks, testing out the electrical and Air Conditioners
on the modulars. Continuing work on the hanging ceiling grids
in the office and children’s area. Primer coat is being applied to
wa...
read more
8/30/2020 Project Update
by: Ron Bloom
08/31/2020
0
We are mudding the drywall in various places within the office
and children’s area. Received inspection by our power company
and the City of Clermont on the electrical interface to the modular
complex. All is a go for power. We have requested a power meter
from SECO to allow us to activate the electrical system for the
modulars. The stone company has completed installation of the
stonework on the front of our sanctuary and the c...
read more
8/23/20 Project Update
by: Ron Bloom
08/23/2020
0
This week has seen a lot of change on the property. Millenium Electric continues to setup the power system that connects with the modular complex. Our next action is to obtain inspections by both the City of Clermont and our power company Sumter Electric. The steel decking for the platform has been completed. Requested inspections so that we can pour the concrete on the decking next week. Sealing up the joints on the wallboard in both the children’s area and the o...
read more
7/10/2020 Project Update
by: Ron Bloom
08/11/2020
0
This week continues with finishing the rough end for the numerous disciplines (plumbing, electrical, fire system, audio visual). Sheet rock
installation continues in the children’s area and starts in the office
area. The sidewalks continue to be poured in the front of the church
as well as both ends of the modular complex.
All the under-platform installations & completion of city inspection
s were done. Closing up the platform wil...
read more
7/25/2020 Project Update
by: Ron Bloom
07/26/2020
0
Hancock Project-Week ending 7/25/2020
This week the building project continued to complete the rough in for electrical, plumbing, A/C and remaining amount of framing. Worked with our Audio-Visual contractor to complete the placement of boxes on the sanctuary platform in preparation for pouring the stage. All insulation has been placed on the sanctuary walls and exterior of the Children’s area. Framed in the AVL booth for the sanctuary. Designed the AVL...
read more